Web Applications WS2015/2016 - Tentative Schedule
Tentative - this will still be changed and adapted.
Week | KW | Date | Topic | Groups/Names | Homework |
---|---|---|---|---|---|
1 | 41 | Thu, 2015-10-08 | e-learning: Rails Startup | – | – |
2 | 42 | Thu, 2015-10-15 | e-learning: Rails Startup | – | – |
3 | 43 | Thu, 2015-10-22 | Introduction, Ruby, Presentation Topics | — | Find Topic and Group for Rails Project (Moodle), Ruby Koans |
4 | 44 | Thu, 2015-10-29 | Settlement of Presentation Topics | BK | Homework 1 |
Rails: Active Record and Associations | BK | ||||
5 | 45 | Thu, 2015-11-05 | Rails: Routing, Active Records Queries, Deployment, Migrations | BK | Homework 2 |
6 | 46 | Thu, 2015-11-12 | Rails: Integration Tests and CI Servers | BK | |
7 | 47 | Thu, 2015-11-19 | Rails: Routing, Patterns and MVC | BK | Homework 3 |
8 | 48 | Thu, 2015-11-26 | Rails: Feature Tests, Session Management in Rails | BK | Homework 4 |
CSS and Responsive Design | Matthias, Simon | ||||
9 | 49 | Thu, 2015-12-03 | NodeJS | Konrad, Joshua und Stefan | Homework 5 - Sprint 1 |
15:45-17:15 | AngularJS | Konstantin, Sebastian, Markus | |||
10 | 50 | Thu, 2015-12-10 | AngularJS | Katia, Ludwig | Homework 6 - Sprint 2 |
15:45-17:15 | JavaScript: Foundations and Manipulating the DOM | ||||
TBD | |||||
11 | 51 | Thu, 2015-12-17 | JavaScript, Ecma 6, AJAX | Christina, Nadine, Tu | Homework 7 - Sprint 3 |
Testing, TDD, BDD, UI-Testing | Lars, Jessica | ||||
14 | 1 | Thu, 2016-01-07 | Build/Release Process: Hosting & Deployment, Continuous Delivery | Tim, Stefan K., Felix | Homework 8 - Sprint 4 |
Build/Release Process: Gulp, Grunt, Yeoman | Oliver | ||||
15 | 2 | Thu, 2016-01-14 | Session Management, Cookies vs. JWT | Max, Stefan N., Michel | Homework 9 - Sprint 5 |
Realtime, WebRTC, Websockets | TBD | ||||
16 | 3 | Thu, 2016-01-21 | Web Security & SSL | Silvio, Maté | Homework 10 - Sprint 6 |
Web Security & SSL, SSL-Zertifizierung | TBD | ||||
17 | 4 | Thu, 2016-01-28 | Persistence NOSQL | Moritz, Arian | Homework 11 - Sprint 7 |
Maps & Geographical Applications | Gley , Ramin | ||||
18 | 5 | Thu, 2016-02-04 | Final Project Presentations | ||
15:45-19:00 | |||||
19 | 6 | Thu, 2016-02-11 | Final Reports Due (Sprint 7 and Presentations) | ||